CONSTRUCTION UPDATES

We are building the Obama Presidential Center in partnership with the community and with City agencies, including the Chicago Department of Transportation, the Chicago Park District, and the Department of Planning and Development. The updates below reflect work by these groups and the Obama Foundation to bring the Obama Presidential Center to life.

August 16, 2021
Obama Foundation Update

The Obama Foundation officially begins work on the Obama Presidential Center after a years-long planning and review process. Roadway improvements will continue and construction will begin within the 19.3 acre site of the Center that sits within the 550 acre Jackson Park.  

Starting this morning, Cornell Drive will begin to be narrowed from six lanes to four lanes between 59th Street and Hayes Drive. At the same time, the easternmost block of South Midway Plaisance, between Stony Island Avenue and Cornell Drive, will be permanently closed.

Motorists that previously used South Midway Plaisance to connect to Cornell Drive will be directed to an alternate route. For northbound motorists, from August 16 to no later than September 2, drivers will need to turn left and go north on Stony Island Avenue and continue up to 57th Street, then turn right on 57th Street to connect up to Cornell Drive and, if desired, continue up to DuSable Lake Shore Drive. Starting no later than September 2, those drivers will still need to turn left and go north on Stony Island Avenue, but only to North Midway Plaisance.

The long-term traffic plan for this area is for North Midway Plaisance to be converted to two-way traffic, and eastbound motorists will then be able to drive “up” North Midway Plaisance from Stony Island Avenue to Cornell Drive. There will be a new signalized intersection at North Midway Plaisance and Cornell Drive.

Ultimately, these new traffic configurations will create better pedestrian connections between the adjacent community, Jackson Park and the lakefront, and better connect currently separated areas of Jackson Park to one another.

CDOT suggests motorists consider the following alternate routes:

For traffic heading to northbound DuSable Lake Shore Drive:

  • 55th Street/Garfield Boulevard to the Dan Ryan/I-90/94 and northbound to I-55 and eastbound to northbound DuSable Lake Shore Drive
  • Cottage Grove to 47th Street and eastbound to northbound DuSable Lake Shore Drive

For traffic heading southbound:

  • 55th Street/Garfield Boulevard to the southbound Dan Ryan/I-90/94
  • 63rd Street eastbound to Hayes Drive and southbound on either Stony Island or South Shore Drive

June 28, 2021
Obama Foundation Update
Beginning today, Cornell Drive will be reduced to 2 lanes in each direction. One southbound lane has been closed, and one northbound lane will be closed later in the day.

This activity marks the start of 6-7 weeks of preparatory work to remove the existing median on Cornell Drive and install a new one.

Construction workers work on Cornell Drive on the South Side of Chicago.

The Foundation is carrying out this construction activity with Lakeside Alliance, who has subcontracted work to Certified Minority-Owned (MBE), Women-Owned (WBE), and Disadvantaged (DBE) electrical company City Lights. This work has been approved and permitted by the Chicago Department of Transportation.

A group of construction workers wearing yellow shirts and white hardhats gather.


June 8, 2021
Chicago Park District Update
Construction work has begun on the utility crossing at Stony Island Avenue between the eastbound and westbound Midway Plaisance Drives.

The northbound curb lane of Cornell Drive and the pedestrian sidewalk east of Cornell Drive is also closed to allow for the utility work.

Utility lines are shown being placed into the ground.

Utility lines are shown being placed into the ground.

The installation of the sanitary sewer across Cornell Drive and at the lift station is anticipated to begin this week.

The track and field work is advancing with the installation of the artificial turf. The turf carpet was installed last week and they are moving on to the installation of the infill material.

A football field is shown from the end zone area.

A football field with the Chicago Bears logo is shown at the 50-yard line.

Check out a complete description of the work being completed in Jackson Park, including lane closures, utility work, and more from the Chicago Park District.


May 24, 2021
Chicago Park District Update
Construction work on eastbound Midway Plaisance Drive will continue this week for the contractor to complete roadway restoration at the location of the utility crossing.

The northbound curb lane of Cornell Drive is now closed in order to allow for the utility work. Additional lane closures have begun on Cornell Drive this week to allow for the utility crossing.

See more updates here.


May 11, 2021
Chicago Park District Update
Construction work on eastbound Midway Plaisance Drive will continue this week with utility work crossing all lanes of eastbound Midway Plaisance, just west of Stony Island Avenue. Utility work is also anticipated to begin crossing Cornell Drive the week of May 17.

See more updates here.


April 27, 2021
Chicago Park District Update
Construction work on eastbound Midway Plaisance Drive and Stony Island Avenue began this week. This is a moving operation with construction flaggers and rolling lane closures.

Upcoming Lane Closures
Midway Plaisance Drive (Eastbound) – Lane closures projected to begin today, and last for approximately one week.

Stony Island Avenue– Lane closures projected to begin on May 10, for approximately one and a half weeks.

See more updates here.


March 16, 2021
Chicago Park District Update
This spring, the Chicago Park District will begin utility relocation work and resume track and field work in Jackson Park. The utility work includes relocating an electrical line, a sewer line and a water line below-ground between Midway and Hayes.

The utility relocation work will occur alongside streets or sidewalks around the edges of the Obama Presidential Center (OPC) site, or south of the OPC site. The existing track and field on that site will remain available for use.

The Park District also has partially completed a new track and field project at the corner of Stony Island and Hayes. As the site has been sitting dormant since 2018, we need to review the current site condition and determine if remedial work is needed prior to completing the full scope of work.

The target start date for commencing both the utility work and the track and field work is April 1st, weather permitting. However, as early as Wednesday, March 17th, residents may see staff and contractors out on these sites so that they can assess the sites and prepare for the upcoming work.

See more updates here.


February 3, 2021
Obama Foundation Update
Obama Presidential Center groundbreaking announced for 2021 as multi-year federal review process concludes. Read more.

Take a closer look at the federal regulatory review process for Jackson Park improvements from the Department of Planning and Development, which also includes a calendar of federal review milestones.

CONSTRUCTION CAREERS

The Obama Foundation helped create the We Can Build It consortium to get more Chicagoans involved in the building trades, especially residents on the South and West Sides. We Can Build It is currently recruiting Chicago-area residents to train for careers in construction, working on the Obama Presidential Center or other projects across the city. 

Work in construction

If you or someone you know would like to be considered for a career in construction, get started here.

Learn more about our workforce initiative

Explore the Obama Presidential Workforce Initiative.

SUBCONTRACT WITH THE OBAMA FOUNDATION

The Lakeside Alliance is leading the construction of the Obama Presidential Center and brings together four of the largest, most respected African-American-owned firms in Chicago, with one of the largest construction management firms in the US. Currently, they are managing subcontractors for the project.

Subcontract with the Center

If you would like to bid on the construction of the Obama Presidential Center, share more information with the Lakeside Alliance.

Offer other services

If you would like to offer other services to the Obama Presidential Center, tell us more about your work.

ADD YOUR VOICE

Top