Obama Presidential Center construction update Sept. 2025: Heading into fall

Get a glimpse into the construction work happening at the Obama Presidential Center campus.

An image of the Obama Presidential Center campus with construction. The picture features an aerial view of the entire campus. In the center is the Museum Building with a crane on top. To the left of the Museum Building is a lake and trees. To the right of the building is Jackson Park.

The Obama Presidential Center is less than a year away from opening, and construction crews are busy across the campus. Teams have been working together to bring several areas of the Center to life before we open our doors in spring 2026. The 19.3-acre campus will feature a one-of-a-kind Museum, a community hub, a new branch of the Chicago Public Library, and Home Court, an athletics and recreation space, as well as dozens of outdoors spaces available to visitors year-round. Built on Chicago’s South Side near where the Obamas’ story began, the Center will be a new global home for civic and community participation.

Take a look at what’s developing at the Obama Presidential Center campus!

The Museum Building

The Obama Presidential Center Museum features dynamic opportunities for visitors to explore the history of the Obamas and the incredible people who helped shape their legacy.

An image of the Obama Presidential Center landscape with the Obama Presidential Center Museum in the background. In the front of the image are planted trees surrounded by soil and dirt. In front of the trees and dirt are flags and construction cones. In the background is the Museum Building with a crane on top of the building. Next to the trees is a dirt path. It is daylight outside and the sky is blue.
A view of the Obama Presidential Center landscape with the Museum Building in the background.
  • Construction: Crews continue to make steady progress installing the last glass panels at the Sky Room Vista. In late August, bronze installation began around the windows of the Museum Building. The eight-story Museum Building is designed to look like four hands coming together and offers some of the most sweeping public views of Chicago from the South Side.

  • Exhibition Installation: The Museum Team has made significant progress on the installation of the Museum exhibition galleries, including the Opening the White House exhibit, which will feature iconic moments from the Obama Presidency in miniature. Once completed, the Museum will include immersive films, artifacts, art installations, and interactive digital programs for visitors to explore.

A rendering of the Obama Presidential Center Museum Building. The image is an aerial image of a conceptual rendering of the Museum tower. In the center of the image is the museum structure: it is a tall beige building. On the roof of the building is grass. On the side of the building are the words from President Obama’s speech on the 50th Anniversary of the March from Selma to Montgomery. Surrounding the building is an aerial of the grassy areas of Jackson Park.
A final rendering of the Obama Presidential Center Museum Building from the Southwest Corner.

The Forum Building

At the Forum Building, work continues on the Elie Wiesel Auditorium, the Hadiya Pendleton Atrium, and the Democracy in Action Lab. 

An image of construction of the Elie Wiesel Auditorium. The top and the back wall of the Auditorium is covered in brown wood paneling with light fixtures. In the center of the image are several beams and pieces of wood. These pieces will become the stage and seats in the Auditorium.
A behind the scenes look at construction on the Elie Wiesel Auditorium
A digital rendering of the Elie Wiesel Auditorium. Tiered seating surrounds an open floor space. Lighting and speakers hang from the ceiling.
Elie Wiesel Auditorium digital rendering, surround seating set-up
  • Elie Wiesel Auditorium: Named after Nobel Prize winner and human rights activist Dr. Elie Wiesel, wood panel installation has been completed on the ceiling in several areas, including the production booth. Workers are also assembling the platforms for the first three rows of auditorium seats that wrap around the stage. 

  • Democracy in Action Wing Lab:  The first white board-covered cabinets were installed in four program rooms. The space will be the campus’ home for all types of programming and civic action, giving burgeoning leaders an opportunity to explore solutions to our world’s most pressing issues.

  • Hadiya Pendleton Atrium: Named in memory of Hadiya Pendleton, a Chicago teenager who was tragically killed just days after performing for the President’s inauguration, the atrium will be a welcoming space that allows people to gather and connect with each other. Workers recently installed the pendant lights in the lobby space of this atrium, where granite panels are being installed on exterior walls. 

Home Court at the Obama Presidential Center

This 45,000 square-foot space will host a variety of youth and adult programming, professional conferences, and community events.

An image of construction being done on Main Court, the Obama Presidential Center's basketball court, at Home Court. The wood panels are on one wall and are brown with blue borders. Each panel of wood is a triangular or diamond shape. Next to the wood panel wall is a glass window. In front of the off the wall are two construction workers on a red crane installing the panels.
Wood paneling being installed by a construction team on Main Court at Home Court
A rendering of Main Court at Home Court on the Obama Presidential Center campus. Main Court is a large basketball court with white ceilings and a wood basketball floor. On the floor is a blue logo of the Obama Foundation. On the left wall is the wood panel with a black scoreboard sitting on top of it. On the right wall are two levels of bleachers where people are seated. In the background are two levels of blue walls with murals on each. On the basketball court are several people wearing athletic gear.
A final rendering of Main Court featuring a basketball game!
  • Open Doors: The Home Court construction team installed the front doors to the main entrance of the building, allowing people to walk through the double set of fritted glass front doors for the first time.

  • Main Court: Inside Home Court is an NBA-regulation basketball court called Main Court. The installation of wood panels is near completion at Main Court and a black rectangle has been erected on the north wall, awaiting the installation of a scoreboard. 

  • Program Rooms: Home Court will also host seven program rooms to be used for community programming, wellness workshops, special events and other activations. Right now, wood cabinets, credenzas, and shelves are being installed, while finishing trimwork is being added around doors and windows. 

Outdoor Spaces

The Obama Presidential Center will feature dozens of outdoor spaces such as the Great Lawn, the Wetland Walk, the Playground, and the Women’s Garden, which are designed to promote wellness, and highlight native trees and plants.

  • Landscape: The first perennial plants recently arrived at the Center with groundcover being added at the south and east sides of the campus, and the first sod has been laid at the Great Lawn. The campus will feature dozens of native plants and vegetation for visitors to learn about, explore, and enjoy. 

  • Eleanor Roosevelt Fruit & Vegetable Garden: Exterior granite has been installed around on the exterior facade of the Eleanor Roosevelt Fruit and Vegetable Garden pavilion, which is located above the campus’ Chicago Public Library Branch. It will serve as a warm and welcoming environment for people to explore gardening, food, and cooking as a pathway to wellness and community improvement. 

  • Playground: Swings have been added to the upper playground area, along with two large slides. When completed, the 21,000 square foot space will also include  a duck slide for toddlers, a giant dragonfly and spiders-web themed rope activities. 

A map of the various buildings and outdoor spaces of the Obama Presidential Center Campus. Green space and paths weave between them. The area is bordered by city streets and, on the opposite side, a lagoon.
Map of the Obama Presidential Center campus

This is a little sneak peek into what’s happening across the campus today. Keep an eye out for more updates as we build the Obama Presidential Center! 

SUPPORT THE OBAMA PRESIDENTIAL CENTER

Your gift today will empower, inspire, and connect the next generation of changemakers. Let’s never stop moving toward the world we want. Make your gift today!

The Barack Obama Foundation is registered as a 501(c)(3) nonprofit organization (EIN 46-4950751).

More construction updates

An upward image of the Obama Presidential Center Museum building during construction. The building is made of granite and stone. In the center of the building is "Uprising of the Sun," an art installation created by artist Julie Mehretu. Around the building are large scaffoldings. Behind the building are clouds.
  • The Center
  • Building the Center

Have you been keeping up with our Construction Updates? Here's our big 2025 mid-year recap!

Learn more
missing
  • Building the Center
  • Sustainability

Celebrate Sustainability Month with us and take a look at the latest developments at the Presidential Center

Learn more
Two bluish purple inverted triangles of wall substructure look to be wedged into the ground on the north face of Home Court, hinting at the shape of the metal panels that will eventually cover this part of the building, and the shape of glass walls between the wedges. In the foreground concrete angular and curved support walls and railings, and contours of geofoam span the landscape where the playground and part of the great lawn will eventually be.
  • Building the Center
  • Chicago

Get a peek at the basketball hoop-shaped exterior wedge walls.

Learn more
A tall, concrete and stone building under construction towers high into the sky. Scaffolding and a crane can be seen on the sides.
  • Building the Center
  • Chicago

The Home Court at the Obama Presidential Center was topped out —which means the steel skeleton of the building is complete!

Learn more
 A silver pickup truck is parked in front of steel beams forming the shape of a large building. At the top is an American flag blowing lightly in the wind. A cloudy sky  and a large crane can be seen behind the building.
  • Building the Center
  • Chicago

The Home Court at the Obama Presidential Center was topped out —which means the steel skeleton of the building is complete!

Learn more
A large concrete building under construction towers ahead. Burnt-orange scaffolding can be seen running from the bottom to the top, many stories high.
  • Building the Center
  • Chicago

Get a peek at the steel framing for the athletics facility, museum building stone installation and an update on the latest artwork.

Learn more
A gray stone installation climbs up the north and east faces of the Museum Building at the Obama Presidential Center. Blue tarp-wrapped escalator bases are seen through an opening that will eventually be clad in an art glass installation. A clear blue sky is in the background.
  • Building the Center
  • Chicago

Concrete construction across the site is complete. The Sky Room and Oval Office are taking shape.

Learn more
On a clear blue-sky day, President Obama stands in a hard hat and a brightly colored safety vest at the Obama Presidential construction site and signs a beam. A large group of construction workers with various skin tones also wearing safety clothing surround him.
  • Building the Center
  • Chicago

The Museum Building at the Obama Presidential Center has reached its final height of 225 feet.

Learn more
President Obama is smiling wearing sunglasses, a white hardhat with the Obama Foundation rising sun logo, gloves, and a bright orange safety vest over a long dress coat. He is holding a cup of coffee and standing next to a white woman wearing a neon yellow construction coat, hard hat, and goggles. They are walking in front of three other people with a range of light to deep skin tones wearing orange safety vests and white hard hats. They are all walking in an unfinished building with scaffolding in the background.
  • Building the Center
  • Chicago

See the latest photos and stay up-to-date on the building process.

Learn more
A view of the Museum Building rising to the sky on the site of the Obama Presidential Center. Cranes are in the sky as work continues on the garage rooftop. Construction equipment is scattered throughout.
  • Building the Center
  • Chicago

The days may be getting cooler, but things are heating up at the Obama Presidential Center!

Learn more
A construction worker in a white hard hat and orange safety vest looks at a structure as he stands on  the concrete floor of Museum Building Level 3
  • Building the Center
  • Chicago

Construction has reached the third floor, where a reconstruction of the Obama Oval Office will be on exhibit.

Learn more
On a clear day, a crane rises up behind a concrete building that’s under construction. In the foreground sits a rust-colored industrial trash bin and to the right, a construction worker wearing a white hard hat and yellow safety vest looks down at a pile of building material.
  • Building the Center
  • Chicago

It has been a season of great progress! The height of the stair and elevator wells have passed the halfway-point of the building.

Learn more
A massive crane stands high above a construction site.
  • Building the Center
  • Chicago

Work on the Museum building has reached an exciting milestone with the placement of the street level deck to form the concrete floor at this level.

Learn more
A construction site with scaffolding, concrete and rebar. Two people wear neon yellow and hard hats on the right side.
  • Building the Center
  • Chicago

Major structural work on the underground parking garage is complete!

Learn more
Two construction workers wearing bright orange and yellow vests  and white hard hats appear to unload planks of wood. They stand in a cavernous room of concrete filled with insulation and other building materials.
  • Building the Center
  • Chicago

As the Center continues to take shape, we are thrilled to reach a new milestone in its construction.

Learn more
A building being constructed of concrete at the Obama Presidential Center. Beams and rebar can be seen in scaffolding. A worker is wearing orange and working in the background. The sky is gray.
  • Building the Center
  • Chicago

Construction at The Center has picked up considerably since the holidays, aided by the unseasonably mild weather.

Learn more


 A wide shot of the construction on the site of the Obama Presidential Center in the daytime.
  • Building the Center
  • Chicago

As construction of the Obama Presidential Center enters its second year, the focus is almost entirely on concrete.

Learn more
missing
  • Building the Center
  • Chicago

The organization is on track to meet its ambitious workforce and business diversity goals for construction.

Learn more
A construction site showing scaffolding and rebar
  • Building the Center
  • Chicago

The majority of columns for the lower level of the parking garage have been cast and construction of the concrete walls is nearly complete.

Learn more
People wearing neon yellow safety gear gather around Barack Obama as he shakes hands with a woman in the center. A white tarp is behind them.
  • Building the Center
  • Barack Obama

Watch as President Obama surprises the construction crew and tours the site.

Learn more
A wide view of a construction site with metal pilings and rebar.
  • Building the Center
  • Chicago

Mass excavation and earth retention is complete and the focus is now squarely on concrete operations.

Learn more
A construction site with concrete and scaffolding. A building is at the center with a red scaffold in the middle.
  • Building the Center
  • Chicago

Two tower cranes were installed to facilitate the construction of the Garage and Museum Building.

Learn more
A construction site filled with mud and concrete. Large metal tubing is on either side and a wood staircase is in the back center of the frame.
  • Building the Center
  • Chicago

A metal perimeter around the subterranean level of the main buildings and parking garage will prevent water from infiltrating the buildings.

Learn more
A wide shot of snow-covered ground and buildings in the background. The sun is shining in a blue sky.
  • Building the Center
  • Chicago

Progress on constructing the Obama Presidential Center continues with relatively few inclement weather delays.

Learn more
A snowy, muddy construction site with the rectangular outline of metal and red pipe.
  • Building the Center
  • Chicago

Drilling for geothermal wells is nearly complete, and work to connect the wells through a series of lateral ducts is about a third of the way finished.

Learn more
Two men in neon yellow construction jackets and hardhats stand waist-deep in a dirt trench. Behind them are construction vehicles and a blue sky with buildings.
  • Building the Center
  • Chicago

Drilling began for the first caissons that will support the underground parking garage.

Learn more
People explore the sky room of the future Obama Presidential Center
  • Building the Center
  • Chicago

This event will bring members of the disabilities community up to speed on the current approach to inclusive design at the OPC.

Learn more
Barack and Michelle Obama with shovels in their hands, smiling at the camera, pretending to dig in a pile of dirt. A man stands on one side of them, Mayor of Chicago Lori Lightfoot holds a shovel on the other side.
  • Building the Center
  • Barack Obama

Mayor Lightfoot and Governor Pritzker joined President and Mrs. Obama for the ceremony, each sharing remarks.

Learn more
A slightly-angled graphic rendering of a large, white rectangular building surrounded by green fields, white pathways and trees. A road is on one side and a body of water on the other.
  • Building the Center
  • Chicago

Roadway improvements will continue and construction will begin within the 19.3 acre site of the Center that sits within Jackson Park.

Learn more
A mostly green and gray site-plan map of the Obama Presidential Center with a focus on buildings, pathways and roads.
  • Building the Center
  • Chicago

Expect lane closures as preparatory work to remove the existing median on Cornell Drive and install a new one begins.

Learn more