Skip to content

Construction Updates

The Obama Presidential Center

Share
People wearing neon yellow safety gear gather around Barack Obama as he shakes hands with a woman in the center. A white tarp is behind them.

We are building the Obama Presidential Center in partnership with the community and with City agencies, including the Chicago Department of Transportation, the Chicago Park District, and the Department of Planning and Development. The updates below reflect work by these groups and the Obama Foundation to bring the Obama Presidential Center to life.

December 8, 2023

Obama Foundation 

Cold weather has arrived in the city, but that hasn’t slowed down construction of the Obama Presidential Center. Crews continue to make steady progress on the concrete structure of the Museum Building, with exterior walls now at Level 6 (a mechanical floor), while the elevator and stairwells remain one level ahead, at Level 7, where the Presidential Suite will be located. Steel framing is being installed to prepare the window openings for glass installation. 

Exterior stone cladding work has begun near the main entrance to the Museum and granite quarried in New Hampshire will clad the Museum, Library, and Forum Buildings. The Forum Building concrete structure is complete, which means that the shorter tower crane will soon be removed. Inside the Forum, spaces like the auditorium, program rooms, and offices are taking shape as interior walls are framed in. The Library Building’s exterior walls and rooftop have been poured and on its rooftop the walls of the Fruit & Vegetable Garden Pavilion are being poured. 

At the south end of the site, the giant, white domed “huddle tent” is being dismantled to make way for the Programs & Athletic Center, which will begin construction in early 2024. The Chicago Department of Transportation’s work to widen Stony Island Avenue is anticipated to be completed by the end of the year.

At the end of November, progress towards ambitious workforce and business diversity goals for construction reflected the following:

  • 53 percent of construction contracts have been awarded to diverse vendors.

  • 35 percent of the workforce hired live in the South and West Sides of Chicago.

  • 257 candidates in jobs around the city.

President Obama is smiling wearing sunglasses, a white hardhat with the Obama Foundation rising sun logo, gloves, and a bright orange safety vest over a long dress coat. He is holding a cup of coffee and standing next to a white woman wearing a neon yellow construction coat, hard hat, and goggles. They are walking in front of three other people with a range of light to deep skin tones wearing orange safety vests and white hard hats. They are all walking in an unfinished building with scaffolding in the background.
An aerial view of the site of the Obama Presidential Center on a foggy day. A concrete structure with scaffolding is in the middle with the Museum of Science and Industry, lagoon, Jackson Park, and Lake Michigan in the background, and the east end of Midway Plaisance to the left.
Workers on a scissor lift install granite panels on the south face of the Museum Building at the site of the Obama Presidential Center. They are wearing yellow safety vests and white hard hats. A clear blue sky is in the background.

October 16, 2023 

Obama Foundation

The days may be getting cooler, but things are heating up at the Obama Presidential Center! Crews onsite are preparing to install the first granite panels that will clad the Museum Building.  This will be the most visible change in the next few months, but the Museum and Forum Buildings are also experiencing a lot of changes. Steel framing of the Auditorium has begun and the footprint of the Hadiya Pendleton Winter Garden can be understood for the first time. 

Down at the Lower Level, framing of the office space is in full swing. As shoring is removed, the future public spaces at the lower and street level of the Museum Building are also becoming defined. The relationship between the different spaces and the volume of the spaces is becoming distinguishable. Natural light is also starting to peek through. Work also continues on the Museum structure, with the elevator and stair cores now rising up to Level 6 at just over 150 feet tall. The floor slab for the top Exhibit Gallery will be poured later this month. The construction trailers and "huddle tent" that have served as the projects operations base for the last two years is being decommissioned so that the south end of the site can be prepared for construction of the Programs & Athletic Center, which will start in early 2024.

A view of the Museum Building rising to the sky on the site of the Obama Presidential Center. Cranes are in the sky as work continues on the garage rooftop. Construction equipment is scattered throughout.
Five workers stand on the platform in the north end of the Hadiya Pendleton Winter Garden. The columns on the left will frame the walls of the auditorium. Construction equipment is scattered throughout the building.

September 1, 2023

Obama Foundation

It has been a season of great progress on the construction of the Obama Presidential Center. The height of the stair and elevator wells of the Museum Building have passed the halfway-point of the building—around 100 feet high—and the concrete walls and floors are following closely behind. Construction crews are now readying the Museum Building for its next critical operation: the installation of the granite and glass that will create the exterior finish of the Museum, Forum, and Library Buildings. The granite will begin to be installed after Labor Day.

The Forum and Library Building roofs are being framed and crews have begun pouring concrete. When that work is complete, the full height of the Forum and Library will be visible above the construction fence!

At the end of June, Cornell Drive was fully closed and the concrete and the asphalt roadway was removed. For the first time, it’s now possible to imagine the eventual connection between the Center’s campus and the Jackson Park lagoon. The entire east side of the campus will create rich habitats for birds and wildlife and will feature a brand new walking and bike path along the edge of the lagoon for visitors to enjoy.

A bulldozer sits in the middle of what was Cornell Drive, where asphalt has been removed revealing a wide dirt pathway. Trees and greenery stand between the former road and the lagoon and on the other side, a rusted metal dumpster filled with debris and various piles of construction materials dot the east side of the main construction zone.

The asphalt and concrete of what was formerly a portion of Cornell Drive has been removed to reconnect the Center’s campus to Jackson Park.

On a clear day, a crane rises up behind a concrete building that’s under construction. In the foreground sits a rust-colored industrial trash bin and to the right, a construction worker wearing a white hard hat and yellow safety vest looks down at a pile of building material.

Crews working at the Southwest corner of the Obama Presidential Center Museum building.

July 3, 2023

Obama Foundation

We are proud of the progress made on the construction of the Obama Presidential Center. At the Museum Building, the elevator and stairwell concrete work has reached the third floor of the Museum Exhibit Galleries where visitors will get a taste of life in the White House and where they can experience a full-scale replica of the Oval Office as it was during the Obama Administration!

The street level concrete floor slabs for the Forum and Library Buildings are mostly in place and the outside walls of those buildings are currently being framed and poured. 

The construction team has installed a hoist to aid the movement of tradespeople and materials up and down the Museum Building. We also expect the City of Chicago to fully close Cornell Drive along the eastern side of the site so that crews can begin work of reclaiming that six-lane road back into green space.

At the end of June, progress towards ambitious workforce and business diversity goals for construction reflected the following:

  • 61 percent of construction contracts have been awarded to diverse vendors.

  • 31 percent of the workforce hired live in the South and West Sides of Chicago.

  • 1 candidate in jobs around the city.

A construction worker in a white hard hat and orange safety vest looks at a structure as he stands on  the concrete floor of Museum Building Level 3

Construction worker stands on the concrete floor of Museum Building Level 3.

A view from the garage Lower Level shows the opening at the north end of the garage where visitors can exit on foot into the Entry Court between the Library and Forum Buildings and into the Plaza.

From the garage Lower Level, the opening at the north end of the garage where visitors can exit on foot into the Entry Court between the Library and Forum Buildings and into the Plaza.

May 5, 2023

Obama Foundation

Construction crews continue to make great progress on the Obama Presidential Center. At the Museum building, concrete work continues on the elevator and stair cores and the exterior walls as crews make progress upwards floor by floor. When complete, the Museum will be a total of 8 floors with a complete height of approximately 225 feet. Work on the Museum building has also reached an exciting milestone with the placement of the street level deck to form the concrete floor at this level.

Concrete work continues at the Forum and Library buildings as crews work to complete the street level floor slabs for each. Street level walls in these buildings are also starting to be formed. Minor work in the underground parking garage progresses as major structural work in the garage has been completed. Mechanical, electrical, and plumbing trades continue to install systems across the campus.

A construction site with two workers smoothing a large concrete pour.

Two workers engaged in concrete finishing work on the street level Museum deck.

A massive crane stands high above a construction site.

The lower level of the Forum building is completely decked over as crews pour the street level floor slab of the building. In the background, is the nearly complete underground parking garage. As the project progresses, landscape with slope over the garage and form the height of the sledding hill.

At the end of March, progress towards ambitious workforce and business diversity goals for construction reflected the following:

  • 52 percent of construction contracts have been awarded to diverse vendors.

  • 31 percent of the workforce hired live in the South and West Sides of Chicago.

  • 287 candidates in jobs around the city.

April 14, 2023

Obama Foundation Construction crews continue to make progress on the Obama Presidential Center. We are thrilled to reach a new milestone in its construction: The southernmost of the three cranes is now being disassembled, as the major structural work on the underground parking garage is complete!

At the Museum Building, the construction of elevator and stair cores and the exterior walls continues to climb upward and work is now visible from outside the construction fence. The concrete is piped up from the ground through special machinery which is now visible atop the highest floor. The Museum Building will ultimately be 225 feet tall, which is approximately the height of the apex of the construction crane.

Crews are also placing overhead mechanical systems throughout the lower level of the buildings and work continues in the major mechanical rooms. Structural concrete work continues in the Forum and Library buildings and the support deck for the street level concrete floor of the Forum Building is nearly complete. That will pave the way for workers to begin pouring the street level floor slab.

A construction crane towers over a building site with a partially built building. The sky is deep blue with wispy clouds.
A construction site with scaffolding, concrete and rebar. Two people wear neon yellow and hard hats on the right side.

March 14, 2023 Obama Foundation

The floor slab on the underground level of the Forum and Library Buildings is almost completely poured and work has begun to build the support deck for the street level floor of the Forum Building. Floor slabs for both levels of the two-story parking garage have also been poured and the roof at the northern end of the garage has also been installed.

As the Center continues to take shape, we are thrilled to reach a new milestone in its construction: There are now spaces in the Forum and Library where other construction trade work can begin! In the lower level of the parking garage, piping from the geothermal wells that were drilled at the start of construction are being extended and collected together in a set of “manifolds” that will support all of the Center’s heating and cooling equipment.

Additionally, at the northeast corner of the underground level of the Museum Building, one of two major mechanical rooms that will serve the building is now being built.

Two construction workers wearing bright orange and yellow vests appear to unload planks of wood. They stand in a cavernous room of concrete filled with insulation and other building materials.

March 14, 2023 Obama Foundation

At the end of January, progress towards ambitious workforce and business diversity goals for construction reflected the following:

  • 54 percent of construction contracts have been awarded to diverse vendors.

  • 31 percent of the workforce hired live in the South and West Sides of Chicago.

  • 228 candidates in jobs around the city.

January 26, 2023 Lakeside Alliance

Today, the Lakeside Alliance, builder of the Obama Presidential Center, released its 2022 Diversity, Equity & Inclusion Report Opens in a new tab . Read the report to see how the Obama Foundation and the Alliance are working together to transform construction in Chicago and beyond.

January 18, 2023 Obama Foundation

Construction at the Obama Presidential Center has picked up considerably since the holidays, aided by the unseasonably mild weather. Concrete floors, columns, and walls are being poured at the Museum, Forum, and Library buildings. The elevator and stairwells can now be seen rising above the construction fence surrounding the site, rising up to around the fourth level, which is one of the Museum exhibit floors.

Additionally, both levels of the underground parking garage have been completed toward the south end of the campus. Work is still being done on the outside walls of the garage and upper level columns will be installed to support the roof of the structure in the Spring. The garage roof will eventually be covered by the Great Lawn—set to be the best sledding hill on the South Side.

A building being constructed of concrete. Beams and rebar can be seen in scaffolding.

January 6, 2023 Obama Foundation

At the end of 2022, progress towards ambitious workforce and business diversity goals for construction reflected the following:

  • 53 percent of construction contracts have been awarded to diverse vendors.

  • 31 percent of the workforce hired live in the South and West Sides of Chicago.

  • 228 candidates in jobs around the city.

September 30, 2022 Obama Foundation

The Foundation is committed to staying on track to meet its ambitious workforce and business diversity goals for construction. Highlights for the month include:

  • 55 percent of construction contracts have been awarded to diverse vendors.

  • 32 percent of the workforce hired live in the South and West Sides of Chicago.

  • 204 candidates in jobs around the city.

September 28, 2022 Obama Foundation

As construction of the Obama Presidential Center enters its second year, the focus is almost entirely on concrete. At the Museum Building, the northern elevator core is poured up through the plaza level and is framed up through to the lobby mezzanine, which represents the first element of the project that can be seen “out of the ground”. The southern elevator core at the Museum Building is also now poured up through the plaza level.



 A wide shot of the construction on the site of the Obama Presidential Center in the daytime.

Elsewhere at the Museum Building, a majority of the perimeter walls are now cast up to the plaza level and preparations are being made for some of the first slab-on-grade pours at the garden level.

At the Forum and Library buildings, most of the grade beams and sub-grade perimeter walls have been cast.

Both levels of the parking garage have been formed up and approximately half of the lower level slab on grade has already been poured.

Update from CDOT

Construction continues on the planned transportation improvements in and around Jackson Park, with crews making great progress on DuSable Lake Shore Drive, Hayes Drive, and Stony Island Avenue.

Please note the following upcoming traffic changes: Starting on or after October 3rd and lasting approximately three weeks, a temporary configuration will go into place to allow for advance work in preparation for construction of two new pedestrian underpasses at the reconfigured intersection of Hayes Drive and Cornell Drive:

  • Hayes Drive between Stony Island Avenue and Cornell Drive will be temporarily closed.

  • Temporary lane reductions will go into place on Cornell Drive to the north and south of the Hayes Drive intersection. During peak rush periods, two lanes of traffic will be maintained in the peak direction. During off-peak periods, one lane will be provided in each direction.

  • For drivers intending to reach northbound DuSable Lake Shore Drive via Hayes Drive to Cornell Drive to 57th Drive, a signed detour will be in place to direct drivers to DLSD via Stony Island Avenue to Midway Plaisance to Cornell Drive to 57th Drive.

A long-term closure of Hayes Drive east of Cornell Drive will also go into place on October 3rd. Local access to Park District facilities will be maintained via Richards Drive.

A map of Jackson Park Transportaion Improvements

Drivers are urged to pay close attention to flaggers and construction signage when entering and driving through work zones, obey the posted speed limits, and be on the alert for workers and equipment.

August 24, 2022 Obama Foundation

The Foundation is proud to release its first OPC construction workforce report highlighting that the organization is on track to meet its ambitious workforce and business diversity goals for construction. Highlights from the report include the following statistics to date:

  • 52 percent of contracts to date have been awarded to diverse vendors.

  • 32 percent of the OPC’s early workforce hired live in the South and West Sides of Chicago.

  • 158 candidates in jobs around the city.

To maintain transparency throughout the construction of the OPC, the Foundation will share an updated version of this report once a quarter.

July 28, 2022 Obama Foundation

The majority of columns for the lower level of the two-story parking garage structure have been cast and construction of the concrete perimeter walls on the lower level is nearly complete. Further north on the site, deep within the large steel basin that provides protection for the future OPC buildings against the surrounding groundwater, concrete work continues. Within the Museum Building footprint, some perimeter walls have been cast, and the first architectural concrete pours (for elements that will actually be exposed to view in the finished building) are being readied for next week. Unlike the parking garage, which is more conventional, the structural demands and the complex systems infrastructure of the Museum Building require an unbelievable amount of steel reinforcement (or rebar) within the concrete, and detailed and careful coordination between the placement of that rebar and the various conduits and pipes that are either set in, or need to pass through, these walls. Concrete work has also just begun on the Forum Building, with the forming and first pours of several of that building’s grade beams.

Concrete operations have also begun on the Museum building along the perimeter and the first architectural concrete pours for elements that will be visible in the finished building are being prepared.At the Forum Building, Concrete work has begun, with the forming and first pours of several of that building’s grade beams.

A construction site showing scaffolding and rebar
A picture of the OPC construction site.

June 24, 2022 Obama Foundation

During a recent trip to Chicago, President Obama stopped by the construction site in Jackson Park to see the latest developments. While there, he took a tour of the site and met some of the talented tradespeople who are bringing the Center to life.

A group of people wearing neon yellow and orange vests and construction hats pose for the camera. Behind them are trailers with signs reading "Concrete Collective Field Office."
Two men wearing hardhats and neon yellow safety vests stand on scaffolding overlooking dirt and an excavator.
People wearing neon yellow safety gear gather around Barack Obama as he shakes hands with a woman in the center. A white tarp is behind them.

May 17, 2022 Obama Foundation

Mass excavation and earth retention is complete and the focus is now squarely on concrete operations.

At the underground, two-level parking garage, which is a more straight-forward structure, work has advanced rapidly. Almost 33% of the garage’s perimeter walls have already been formed, and much of those walls have already been poured:

A construction site with several large cranes over a concrete wall and dirt field.

Part of the goals for the OPC’s design was to try and minimize the visual impact of the Center within Jackson Park. In addition to the fully underground garage, almost one-third of the Center’s occupiable area is below-gradel, with a series of courtyards to bring natural light into these spaces. What that means from a construction standpoint is that there is a lot of work “in the ground” before the Center’s buildings become visible. Currently, crews are working at a depth of approximately 20 feet below street level to ready the two Museum Building “cores”, which are the areas where that building’s stairs, elevators and mechanical/electric shafts will run up the height of the building:

A wide view of a construction site with metal pilings and rebar.

April 13, 2022 Chicago Department of Transportation

The Chicago Department of Transportation (CDOT) today announced that major work in and near Jackson Park in support of the Obama Presidential Center’s planned opening will begin on April 14, 2022 on Southbound DuSable Lake Shore Drive at 57th Street and other adjacent streets. Southbound DLSD will be narrowed to one lane so construction to expand the roadway to three lanes can begin. The expanded roadway is expected to be completed by traffic patterns and work zones will shift several times over the next year. By late 2023, the new 3rd travel lane on SB DLSD will be complete and opened to traffic.

There will be daytime closures of lanes and parking restrictions on northbound Stony Island, beginning the week of April 18. Hayes Drive will be closed just west of DuSable Lake Shore Drive to allow for site testing beginning on or after April 25.

In case of traffic backups a good alternative route is to exit southbound DLSD at 57th Street and turn onto Cornell Drive which will not be under construction.

Access to Park District fields will be maintained throughout the construction. Visit the Department of Transportation for more information Opens in a new tab .

April 8, 2022 Obama Foundation

Mass excavation and dewatering continues at the area where the Museum, Forum, Library, and Garage will be built. This mass excavation operation is approximately 25 percent complete and is expected to be fully completed at the end of May, pending rain delays.

This week, the concrete pad was installed and a tower crane was moved onsite to facilitate the construction of the Garage. Over the next two weeks, an additional tower crane will be used to construct the Museum Building.

Construction of a trailer village is underway at the southwest corner of the site, across from Hyde Park Academy. The trailers will provide office, meeting, and other onsite support space for the growing project workforce and various consultants. The village will be completed in May.

A construction site with concrete and scaffolding. A building is at the center with a red scaffold in the middle.
A massive red crane towers over a sandy area with tread marks.

March 25, 2022 Obama Foundation

Earth retention system work has been completed at the Obama Presidential Center site, creating a metal perimeter around the subterranean level of the main buildings and parking garage that will prevent water from infiltrating the buildings. Dewatering continues, draining groundwater from within the footprint of the Museum, Forum, Library and Garage. Mass excavation also began this week, which will create fairly constant movement of trucks in and out of the site on the Cornell Drive side, for the next several weeks.

A large, white plastic water container with the words "Griffin" stamped in red. Two flexible pipes run from the bottom.
A construction site filled with mud and concrete. Large metal tubing is on either side and a wood staircase is in the back center of the frame.

March 4, 2022 Obama Foundation

The steel sheeting seen below extends 30-35 feet into a thick clay layer beneath the construction site to form the sides of a basin-like structure that will protect the buildings and Garage from the surrounding groundwater. Groundwater captured in the basin will begin, along with the mass excavation of the dirt in this area to allow for pouring the lowest level concrete caisson caps, grade beams, and floor slabs later this Spring.

Snow covers a construction site. A yellow digger can be seen in the background.

February 18, 2022 Chicago Department of Transportation

The Chicago Department of Transportation (CDOT) is starting construction on long planned transportation improvements in and around Jackson Park coordinated with the Obama Presidential Center and supportive of the Chicago Park District’s South Lakefront Framework Plan.

Starting next week, weather permitting, motorists can expect daily off-peak lane closures for site preparation work on Stony Island Avenue, Hayes Drive, and South DuSable Lake Shore Drive. This will continue through mid-March.

Starting in mid-March, reconstruction work will start on Hayes Drive between Cornell Drive and Richards Drive. The public can expect parking restrictions, lane shifts, and detours of pedestrian paths.

Drivers are urged to pay close attention to flaggers and construction signage when entering and driving through work zones, to please obey the posted speed limits, and to be on the alert for workers and equipment as well as pedestrians, cyclists and other motorists.

February 18, 2022 Obama Foundation

Work to construct caissons to support the buildings and garage at the Obama Presidential Center is completed. Sheeting that will protect the subterranean levels of the Museum, Forum, and Library buildings is ahead of schedule.

Earth retention work remains on track as the site is readied for dewatering and mass excavation that is scheduled to begin in March.

Workers in neon yellow vests and hard hats are in a dirt ditch. A yellow excavator is on the right.
A snowy, muddy construction site with the rectangular outline of metal and red pipe.

February 7, 2022 Obama Foundation

Progress on constructing the Obama Presidential Center continues with relatively few inclement weather delays. By the end of the week, all of the caissons will be drilled. Installation of sheeting all around the Museum, Forum, Library, and Garage structures is almost 50 percent complete. Work has begun to stabilize that sheeting and dewater the area within the sheeting, and the site is being readied for mass excavation which will become the foundation for the Museum, Forum, Library, and Garage structures. In March, the Chicago Department of Transportation (CDOT) is slated to begin a major investment to modernize and expand several roadways in and around Jackson Park, including areas surrounding the Center.

A wide shot of snow-covered ground and buildings in the background. The sun is shining in a blue sky.
A red-and-white striped cement mixer backed up to a large circular drum-shaped object. A man wearing a neon-yellow safety vest stands beside it. Another large piece of construction equipment is on the left side.

January 14, 2022 Obama Foundation

Construction is complete on caissons to support the underground parking garage. Meanwhile, construction of caissons for the Museum, Forum, and Library buildings continues and, as of today, they are approximately 45 percent complete.

Drilling for geothermal wells is nearly complete, and work to connect the wells through a series of lateral ducts is about a third of the way finished. Late next week, work will begin on earth retention and sheeting, which is the process of protecting the building foundations from water and pressure from nearby Lake Michigan and the Lagoon.

A white crane with a ditch of dirt in the foreground. A building is on the left, a parking area on the right.
A snowy, muddy construction site with the rectangular outline of metal and red pipe.

January 5, 2022 Obama Foundation Update

The construction of the Obama Presidential Center rang in the new year by continuing to make progress with the drilling of caissons and other below-grade work. All of the future underground garage caissons are complete, and work on the future Museum Building’s caissons is underway. Earth retention work is planned to start in the next week or so, and the number of construction workers being employed is steadily increasing to a current daily average of approximately 75 persons working on the site in some capacity every work day. To date, more than 40 percent of the total worker hours expended to help build the Obama Presidential Center have been performed by residents of the South and West Sides of Chicago.

December 13, 2021 Obama Foundation Update

This week, drilling began for the first caissons that will support the underground parking garage. Caissons are a network of underground concrete pilings that support structures—in this case, the Obama Presidential Center campus! Preparatory work also began for the caissons that will support the Museum Building. Drilling for those caissons will begin this Monday, December 13.

Drilling and installation of geothermal energy wells continues on schedule.

A construction site with long, black pipes in the foreground, construction vehicles in the background
Two men in neon yellow construction jackets and hardhats stand waist-deep in a dirt trench. Behind them are construction vehicles and a blue sky with buildings.

October 26, 2021 Obama Foundation Update The Foundation will host a community engagement event for People with Disabilities. This event will bring members of the disabilities community up to speed on the current approach to inclusive design in the museum exhibits, share initial thinking around accessibility affordances within the museum experience, and highlight some of the work yet to come.

October 25, 2021 Obama Foundation Update

This week, truckloads of dirt will continue to be hauled off. On the lagoon and Midway Plaisance sides of the site, new asphalt walking paths have been poured to allow for safe walking and biking around the perimeter of the site.

The following activities are also set to begin this week:

  • The site is being rough-graded, with excess topsoil being hauled off through the first week of November, in preparation for the start of below-grade works.

  • In an effort to create an energy-efficient and sustainable campus, the Obama Presidential Center will be powered by geothermal heating and cooling. The system is built upon a network of very deep wells called caissons. Drilling will begin on November 1.

A dark asphalt-paved bike and walking trail is shown in the middle with orange construction fencing on either side of it.
The construction site for the Obama Presidential Center is shown through the links in a metal fence.

September 28, 2021 Obama Foundation Update

The Obama Foundation officially broke ground on site. Mayor Lightfoot and Governor Pritzker joined President and Mrs. Obama for the ceremony, each sharing remarks about the project and the positive impact it will have on the surrounding neighborhoods. Learn more here.

Barack and Michelle Obama with shovels in their hands, smiling at the camera, pretending to dig in a pile of dirt. A man stands on one side of them, Mayor of Chicago Lori Lightfoot holds a shovel on the other side.

August 16, 2021 Obama Foundation Update

The Obama Foundation officially begins work on the Obama Presidential Center after a years-long planning and review process. Roadway improvements will continue and construction will begin within the 19.3 acre site of the Center that sits within the 550 acre Jackson Park.

Starting this morning, Cornell Drive will begin to be narrowed from six lanes to four lanes between 59th Street and Hayes Drive. At the same time, the easternmost block of South Midway Plaisance, between Stony Island Avenue and Cornell Drive, will be permanently closed.

Motorists that previously used South Midway Plaisance to connect to Cornell Drive will be directed to an alternate route. For northbound motorists, from August 16 to no later than September 2, drivers will need to turn left and go north on Stony Island Avenue and continue up to 57th Street, then turn right on 57th Street to connect up to Cornell Drive and, if desired, continue up to DuSable Lake Shore Drive. Starting no later than September 2, those drivers will still need to turn left and go north on Stony Island Avenue, but only to North Midway Plaisance.

The long-term traffic plan for this area is for North Midway Plaisance to be converted to two-way traffic, and eastbound motorists will then be able to drive “up” North Midway Plaisance from Stony Island Avenue to Cornell Drive. There will be a new signalized intersection at North Midway Plaisance and Cornell Drive.

Ultimately, these new traffic configurations will create better pedestrian connections between the adjacent community, Jackson Park and the lakefront, and better connect currently separated areas of Jackson Park to one another.

CDOT suggests motorists consider the following alternate routes:

For traffic heading to northbound DuSable Lake Shore Drive:

  • 55th Street/Garfield Boulevard to the Dan Ryan/I-90/94 and northbound to I-55 and eastbound to northbound DuSable Lake Shore Drive

  • Cottage Grove to 47th Street and eastbound to northbound DuSable Lake Shore Drive

For traffic heading southbound:

  • 55th Street/Garfield Boulevard to the southbound Dan Ryan/I-90/94

  • 63rd Street eastbound to Hayes Drive and southbound on either Stony Island or South Shore Drive

June 28, 2021 Obama Foundation Update

Beginning today, Cornell Drive will be reduced to 2 lanes in each direction. One southbound lane has been closed, and one northbound lane will be closed later in the day.

This activity marks the start of 6-7 weeks of preparatory work to remove the existing median on Cornell Drive and install a new one.

Construction Careers